This solicitation calls for a blanket‑order contract to perform refractory demolition and reinstall work on the wet‑bottom boilers at the John Twitty Energy Center. The contractor must provide labor, supervision, and specific stainless‑steel V‑Anchors and refractory mix materials, while City Utilities supplies temporary power, dumpsters, and limited welding services. The work is “as‑needed” with a planned fall‑outage window in 2027 and includes a one‑year base term with up to four one‑year options. The procurement method is a competitive RFP evaluated on price (up to 70 %) and compliance (up to 30 %). A performance and payment bond is required for bids over $50,000, and prevailing‑wage, insurance, OSHA, and E‑Verify requirements apply.
• Scope: demolition, reinstall, material supply, supervision, and curing recommendations for roughly 819 sq ft of boiler refractory.
• Schedule: initial proposal due 8/14/2026, BAFO deadline 8/26/2026, work window 10/1/2027‑12/17/2027.
• Requirements: Bond, prevailing‑wage compliance, insurance minimums, OSHA safety program, and detailed post‑completion reporting.