The contract is for the regasketing and painting of a 15/20/25 MVA Westinghouse Power Transformer at the 1st Street Substation Bank 1. The engineer's estimate for the project is between $96,000 and $132,000. The contract was awarded to Transfluid Services and Specialty Engineering, Inc. The project requires the furnishing of all materials, labor, tools, and equipment necessary to perform the work.
• The project consists of regasketing, oil testing, and painting the transformer.
• The engineer's estimate is between $96,000 and $132,000.
• The contract was awarded to Transfluid Services and Specialty Engineering, Inc.
• The project requires the furnishing of all materials, labor, tools, and equipment necessary to perform the work.