The contract is for fire damage repairs to the Paradise Courthouse in Paradise, CA. The project includes repairs to structural wood framing, fascia and soffit panels, tear-off and replacement of the roof, and replacement of all rain gutters and downspouts. The contract also includes additional/deductive alternate work, such as removal and replacement of 50' of rain gutter at the Magalia Sheriff's Substation and removal and replacement of carpeting in the Magalia Fire Station #33 living quarters. The engineer's opinion of the cost for the project is between $215,000 and $275,000. The contract was bid on through an Invitation for Bid (IFB) process, and the bid submission date was January 16, 2020.
• The project consists of fire-damaged repairs to structural wood framing, fascia and soffit panels, tear-off and replacement of roof and replacement of all raingutters and down spouts on the Paradise Courthouse, in Paradise, CA.
• The engineer's opinion of the cost for the project is between $215,000 and $275,000.
• The contract was bid on through an Invitation for Bid (IFB) process.
• The bid submission date was January 16, 2020.
• A pre-bid conference was held on December 17, 2019, at 5:00 PM EST.
• A non-mandatory site walk was held on December 17, 2019, at 2:00 PM EST.