Awarded contract·Harris County Purchasing Agent·Texas
20/0347 - Bridge Reconstruction for the Brays Bayou Federal Flood Control Project at Chimney Rock (Discrete Segment 110B) and South Rice (Discrete Segment 110A) for the Harris County Flood Control District
The contract is for the bridge reconstruction of the Brays Bayou Federal Flood Control Project at Chimney Rock and South Rice. The project involves the replacement of two bridges, with a total estimated cost of $20,093,840.80. The contract was awarded to Ragle Inc, a private company that submitted the lowest bid for the project. The contract includes a performance bond and a payment bond, both of which are required by the Texas Government Code. The contract also includes provisions for the payment of claims and the assumption of control of the contract by the surety in the event of default by the principal.
• The contract is for a specific project, the Brays Bayou Federal Flood Control Project
• The project involves the replacement of two bridges
• The estimated cost of the project is $20,093,840.80
• The contract was awarded to Ragle Inc, a private company
• The contract includes a performance bond and a payment bond
• The contract includes provisions for the payment of claims and the assumption of control of the contract by the surety in the event of default by the principal