This contract calls for the removal and replacement of 160 tubes in a 1988 Superior hot‑water boiler (Model 5‑5‑1276L‑GP) and a subsequent alkaline boil‑out cleaning of the boiler and feed‑water system. The work includes front‑end seal‑rolled tube installation, R‑stamp certified welding, hydrostatic testing under an authorized inspector, waste disposal, and coordination with county staff for site access. The award is a firm‑fixed‑price contract valued at $33,797, awarded to a single vendor on a “lowest responsible and responsive” basis. The project must be completed within roughly three weeks of contract start, with a substantial completion target of 14 calendar days and final completion 8 days thereafter.
• Scope: tube replacement, welding, hydrostatic test, boil‑out, waste management.
• Timeline: bid deadline Oct 26 2021; award Nov 19 2021; work to finish within ~22 days.
• Funding: $33,797 fixed‑price; insurance and licensing requirements prescribed.