The Hope Street Academy Chiller Replacement project involves the removal of an existing condensing unit and associated indoor barrel, and the installation of a new condensing unit and indoor plate and frame heat exchanger. The project also includes an add alternate scope of work to provide and install a new pump, as well as an allowance for unforeseen work. The contract was solicited through an Invitation for Bid (IFB) process, and four vendors submitted bids. The bids ranged from $167,406 to $221,800.
• The project involves the replacement of a chiller at Hope Street Academy.
• The contract includes an add alternate scope of work to provide and install a new pump.
• The contract includes an allowance for unforeseen work.
• The contract was solicited through an IFB process.
• Four vendors submitted bids for the project.