The contract is for the replacement of six air handling units at Airside F with high-efficiency, built-in-place units. The project includes the removal and replacement of existing air handlers, as well as the installation of new variable frequency drives and controls. The contract was awarded to Bernhard MCC, LLC, with a contract sum of $1,898,155. The project is expected to be completed within 282 days. The key aspects of the project include the replacement of air handling units, the installation of new variable frequency drives and controls, and the completion of the project within the specified timeframe. Some of the key features of the project include:
• The replacement of six air handling units with high-efficiency, built-in-place units
• The installation of new variable frequency drives and controls
• The completion of the project within 282 days
• The contract sum of $1,898,155
• The requirement for the contractor to provide a full-time quality control manager and to maintain a quality control plan
• The requirement for the contractor to provide insurance coverage, including general liability, automobile liability, and workers' compensation insurance.