This contract is for the UDOT R-163 Flooding Repair project, which involves construction services related to repairing roadway damage and embankment damage caused by recent flooding on SR-163 and SR-316 in San Juan County. The contract was awarded to Staker Parson Companies, with a total bid of $1,408,381.50. The project includes work such as replacing and extending existing culverts, and the contractor must submit a performance and payment bond upon award. Some key points about this contract include:
• The contract is for construction services related to flooding repair.
• The project includes replacing and extending existing culverts.
• The contractor must submit a performance and payment bond upon award.
• The contract was awarded to Staker Parson Companies.
• The total bid for the contract was $1,408,381.50.