The City of Rexburg issued a Qualification‑Based Selection (QBS) RFQ for a Construction Manager/General Contractor (CM‑GC) to deliver a new police‑station facility. The project is estimated at $10‑$17 million and will be executed in pre‑construction and construction phases, with the CM‑GC responsible for managing design coordination, cost estimating, scheduling, sub‑contract procurement, and construction execution once funding is secured. Headwaters Construction Company was awarded the contract. The solicitation required Idaho‑licensed construction managers who also hold a public‑works general‑contractor license, bonding and insurance compliance, and a 90‑day SOQ validity period. The final submission deadline was extended to December 27 2024.
• Scope – Pre‑construction design coordination, cost estimating, value engineering, bid management, and full construction management for a municipal police station.
• Eligibility – Idaho‑licensed public‑works Construction Manager and General Contractor; must provide 100 % performance/payment bonds and specified insurance.
• Timeline – SOQ due Dec 27 2024; anticipated construction start Summer 2026 pending bond approval.
• Award – Headwaters Construction Company selected as the sole CM‑GC vendor.