The City of Richland has awarded a contract for the WWTP Operations Building HVAC Upgrades. The contract includes the installation of HVAC upgrades at the City's Wastewater Treatment Plant. The engineer's estimate for the project is between $88,000 and $120,000. The contract was awarded to McKinstry Co., LLC, with a total price of $125,674.59. The project consists of furnishing all materials, labor, tools, and equipment necessary to complete the installation of the HVAC upgrades.
• The project includes the installation of HVAC upgrades at the City's Wastewater Treatment Plant.
• The engineer's estimate for the project is between $88,000 and $120,000.
• The contract was awarded to McKinstry Co., LLC, with a total price of $125,674.59.
• The project consists of furnishing all materials, labor, tools, and equipment necessary to complete the installation of the HVAC upgrades.
• The City of Richland encourages small, minority, and women-owned firms to submit bids.
• A pre-bid meeting is not scheduled, but bidders can contact Nick Blasdel to schedule a site visit.