This contract awards a pre‑qualified, restricted‑bid construction project to extend a natural‑gas main in the Marabella Subdivision Phase 1 of Springfield, MO. The scope includes extending the gas main, installing service stubs, pressure testing, pavement and landscape restoration, and final purging/operation of new connections. The project must start after 10 / 1 / 2026, be completed by 6 / 30 / 2027, and is subject to a $500 per day liquidated‑damages clause for delays. The winning bid totals approximately $126 k, and the vendor must provide required performance and payment bonds, meet prevailing‑wage and insurance requirements, and be pre‑qualified under the City Utilities program.
• Scope: Gas‑main extension, service stub installation, testing, and site restoration.
• Schedule: Earliest start 10 / 1 / 2026; completion deadline 6 / 30 / 2027 (120 day per‑section limit).
• Financials: Awarded bid $125,982.40; bonds required for bids > $50,000; liquidated damages $500/day.