This contract calls for the design, supply, installation, testing, adjusting, and balancing of new fan‑coil units, a CRAC split system, and related chilled‑water valve work in French Hall at Longwood University, including associated piping, electrical, controls, and finishing work. The award was made to Waco, Inc., a Virginia‑based contractor, under a lump‑sum, sealed‑bid process. The project requires compliance with university construction standards, SWaM participation (minimum 5 % small‑business), a 5 % bid bond, and performance and payment bonds. Completion is required within 120 calendar days for substantial completion and an additional 30 days for final completion.
• Scope: install 2 fan‑coil units, a CRAC split system, bypass chilled‑water valve, replace valves, construct wall chases/ceiling work, and perform all associated mechanical, electrical, and control work.
• Procurement: Invitation for Bid (IFB) with optional pre‑bid conference, sealed‑bid deadline 10/17/2019, public opening 10/18/2019.
• Requirements: Virginia contractor license, eVA registration, bid bond (5 % of bid), performance/pay‑roll bonds, SWaM participation, safety & campus access compliance.