The contract is for the repair of the damaged section of the boardwalk at Tom Hooper park. The work includes the removal of a removable cross section of the boardwalk to allow for repairs by the FDOT contractor. The contract amount is $2,286,804.71, and the contract term is from September 1, 2024, to July 4, 2025. The contract was awarded to Brothers' Construction, Inc. Some key points of this contract include:
• The contract is for the repair of the damaged section of the boardwalk at Tom Hooper park.
• The work includes the removal of a removable cross section of the boardwalk to allow for repairs by the FDOT contractor.
• The contract amount is $2,286,804.71.
• The contract term is from September 1, 2024, to July 4, 2025.
• The contract was awarded to Brothers' Construction, Inc.