The contract is for the expansion of the Goodyear Maintenance Yard, with a project duration of 99 days. The contract includes a change order that extends the timeline by four weeks due to delays in receiving materials. The contract amount is not explicitly stated, but the change order mentions a revised contract amount. The scope of work includes construction activities, site clearing, pipe installation, and asphalt base and paving. The contract is between the City of Goodyear and Talis Construction Corporation.
• The contract is a change order for the Goodyear Maintenance Yard Expansion project.
• The project duration is 99 days, with a revised completion date of 11/26/2025.
• The contract includes a change order that extends the timeline by four weeks.
• The scope of work includes construction activities, site clearing, pipe installation, and asphalt base and paving.
• The contract is between the City of Goodyear and Talis Construction Corporation.