This contract awards H2E Inc. a fixed‑price, end‑to‑end integration effort to replace the City of Spokane’s air‑gapped Wonderware SCADA system at the Upriver Water & Hydroelectric Facility with a new Allen Bradley/Rockwell PlantPAx solution. The City supplies all hardware, installation, and network documentation; the vendor provides system design, PLC programming, PlantPAx configuration, testing, training, and post‑implementation support.
• Scope includes design, migration strategy, new PLC code (System Master & Zone Master), PlantPAx installation on Nutanix VMs, security hardening, and 40 + hours on‑site operator training.
• Deliverables: complete SCADA configuration, documentation packages, O&M manuals, and a support agreement with 1‑hour critical response.
• Project timeline targets contract start 30 May 2025, completion by 31 Dec 2026, with mandatory pre‑bid meeting on 10 Mar 2025 and proposal due 31 Mar 2025.