The Ohio State University is rebidding its FY 23‑24 emergency‑generator replacement program for two campus facilities (Mershon Auditorium and the Wexner Center). The contract is a low‑bid, electronic‑bid solicitation that covers demolition of existing generators, removal of associated fuel tanks and asbestos‑containing components, and installation of new diesel‑engine generators with automatic transfer switches, surge‑protective devices, and new distribution panels. The scope also includes site‑work such as concrete generator pads, fence installation, landscaping, and full compliance with hazardous‑material, prevailing‑wage, EDGE‑participation, and SUPR program requirements.
• Demolish existing generators, fuel tanks, and identified asbestos gaskets/insulation; dispose of hazardous waste per EPA/OSHA regulations.
• Install new 500 A, ~350 kW diesel generators, associated automatic transfer switches, surge protective devices, and re‑route electrical feeders and fire‑alarm circuits.
• Provide civil work: concrete pads, retaining walls, decorative steel fence, landscaping (soil preparation, planting, irrigation), and 462‑day contract time for substantial completion.
• Mandatory compliance items: 5 % EDGE participation, domestic‑steel usage, prevailing‑wage rates, drug‑free safety program enrollment, and detailed documentation (bid guaranty, qualifications, EDGE affidavit, power of attorney).
• Project budget: Base bid $1.185 M with two optional alternates ($55 k and $40 k) for a potential maximum award of ≈$1.28 M.