This solicitation calls for the full replacement of the HVAC infrastructure at the Country Club of Miami, including a new air‑cooled chiller, pumps, eight air‑handler units, associated ductwork, piping, valves, controls, and related accessories. The contractor must handle demolition, installation, testing, balancing, permitting, and coordination with other site trades, delivering a complete, operational system within a one‑year schedule.
• Replace existing air‑cooled chiller (CH‑1) with a new high‑efficiency unit and install associated chilled‑water pumps, expansion tank, air separator, and control valves.
• Supply and install eight new air‑handler units, new ductwork, insulation, electric duct heaters, and necessary mechanical accessories.
• Perform all required permitting, inspections, and testing, provide as‑built drawings, and meet liquidated‑damage and UAP fee requirements.