This solicitation seeks a qualified electrical contractor to design, permit, install, test, and commission a new 1,200 A, 480 V service for Miami‑Dade County’s Resource Recovery Facility, replacing power from the de‑commissioned plant. The contractor must coordinate with Florida Power & Light (FPL) for the primary service hookup, distribute power to four critical load points (lift station, trailer, scale houses/security, maintenance building), and provide temporary power as needed while ensuring compliance with FPL standards, NEC 2020, Florida Building Code 2023, and all local codes. The scope includes detailed design drawings, permit acquisition, installation of conduit, wiring, disconnect switches, grounding, metering, and fire‑stop systems, plus as‑built documentation and warranties.
• Design and obtain permits for a new 1,200 A, 480 V service (FPL coordination).
• Install distribution to four load centers: Lift Station 938 (400 A), Transportation Trailer (≈400 A), Scale Houses 1‑2 & Security (200 A total), Reworld Maintenance Building (up to 250 A temporary).
• Provide full construction‑level work: conduit, raceways, panels, grounding, over‑current protection, fire‑stop sealing, testing, commissioning, and close‑out documentation.
• Meet strict schedule (start ~April 1 2026, complete within 150 calendar days) and extensive bonding/insurance requirements (5 % bid bond, performance & payment bonds, 5 % retainage, 2 % UAP fee).