This solicitation calls for the complete demolition, removal, and replacement of the existing HVAC, boiler, pump, and control systems at the Troop B Headquarters and Crime Laboratory in Macon, MO. The scope includes installing a new air‑cooled chiller, new boilers, pumps, hydronic piping, VAV boxes, indoor/outdoor air handling units, energy recovery units, and a Johnson Controls DDC control system, plus associated electrical work. The project must be phased to maintain occupancy, and the contractor must provide temporary heating and cooling during construction.
• Full demolition of existing HVAC equipment and controls.
• Installation of new HVAC plant, including chillers, boilers, pumps, piping, VAV boxes, AHUs, ERVs, and DDC controls.
• Required electrical upgrades, temporary heating/cooling, and phased construction to keep the facility operational.