The contract is for the recoating of a ground level steel water storage tank and the installation of a perimeter guard rail atop the tank. The work includes surface preparation, application of coating systems, caulking, and compliance with health, safety, and regulations. The contract was awarded to Cal Sierra Construction with a bid of $588,925.00. The project is located at 8246 Waterman Road, Elk Grove, CA 95829.
• The contract requires the furnishing of all labor, materials, and equipment for the recoating of the water storage tank.
• The work includes surface preparation, application of coating systems, caulking, and compliance with health, safety, and regulations.
• The contract was awarded to Cal Sierra Construction with a bid of $588,925.00.
• The project is located at 8246 Waterman Road, Elk Grove, CA 95829.
• A mandatory pre-bid conference was held on August 11, 2016, at 2:00 PM at the project site.