The City of Ridgefield has awarded a contract for construction management services for the Pioneer Widening and 50th Avenue Roundabout Project. The project involves constructing roadway widening, joint utility and sanitary sewer improvements, and a roundabout at Pioneer and 50th Avenue. The contract was awarded to Consor North America, Inc. The project is expected to last for 19 months, and the contract value is estimated to be around $1.8 million. The key aspects of the project include providing all construction management and inspection services, overseeing project tasks, and coordinating with the City of Ridgefield, Clark Regional Wastewater District, and Washington State Department of Transportation representatives. Some of the key challenges identified by the evaluators include staging, traffic management, and utility relocation. The contract document also mentions the evaluation criteria and scores for different consultant teams, including RS&H, Dowl, and Consor.
• The project involves constructing roadway widening, joint utility and sanitary sewer improvements, and a roundabout at Pioneer and 50th Avenue.
• The contract was awarded to Consor North America, Inc.
• The project is expected to last for 19 months.
• The contract value is estimated to be around $1.8 million.
• The key aspects of the project include providing all construction management and inspection services, overseeing project tasks, and coordinating with the City of Ridgefield, Clark Regional Wastewater District, and Washington State Department of Transportation representatives.
• Some of the key challenges identified by the evaluators include staging, traffic management, and utility relocation.