The Water Line Improvement Project involves the installation of new water lines and partial replacement of existing lines on the California Polytechnic State University, San Luis Obispo campus. The project has a duration of 82 calendar days and a total bid amount of $373,113. The successful bidder, HPS Mechanical, Inc., has committed to achieving 3% DVBE participation in the project. The project also involves the rental of equipment and materials, and the bidder has listed its proposed subcontractors and suppliers. Some key points about this project include:
* The project is a public works project subject to prevailing wage rate laws.
* The bidder has submitted a bid proposal form, which includes the total amount of the base bid and the proposed subcontractors and suppliers.
* The bidder has also submitted a bidders' bond, which guarantees the bidder's performance and payment for labor and materials.
* The project has a liquidated damages clause, which imposes a penalty of $500 per day for delays in completion.
* The bidder has committed to achieving 3% DVBE participation in the project, and has listed its proposed subcontractors and suppliers.
* The project involves the rental of equipment and materials, and the bidder has declared that it will comply with the prevailing wage rate laws.