The contract is for the replacement of the A & C Guideways running surface at Tampa International Airport. The work includes the removal of the existing concrete surface, the installation of a new concrete surface, and the replacement of bearing pads. The contract also includes provisions for liquidated damages in the event of delays. The contractor, Johnson-Laux Construction, LLC, has provided a detailed price proposal for the project, including a breakdown of the costs for various components of the work. Some key points about the job's work and scope-of-work include:
* The project involves the replacement of the A & C Guideways running surface at Tampa International Airport.
* The work includes the removal of the existing concrete surface, the installation of a new concrete surface, and the replacement of bearing pads.
* The contract includes provisions for liquidated damages in the event of delays.
* The contractor is required to provide a new circuit for the temporary canopy lights and to perform work during daytime and nighttime shifts.
* The contract includes a detailed breakdown of the costs for various components of the work, including labor, materials, and equipment.
* Some of the specific tasks included in the contract are:
* Removal of the existing concrete surface
* Installation of a new concrete surface
* Replacement of bearing pads
* Installation of a new circuit for the temporary canopy lights
* Performance of work during daytime and nighttime shifts
The contract has a total value of $5,271,271.83 and is expected to be completed within 905 days.