This contract calls for the replacement of deteriorated decking and fasteners along Wilmington’s Riverwalk, a high‑visibility public waterfront promenade. The work is limited to decking and minor framing repairs; major structural work and corroded toe‑curb bolts are excluded. The contractor must secure all required permits (including a CAMA permit), handle any temporary electrical shutdowns, and complete the work within a five‑month window. The solicitation required a single‑prime sealed bid, includes a 14 % MBE/DBE subcontracting goal, and imposes liquidated damages of $230 per day after the 360‑day period.
• Scope: decking and fastener replacement (Option A), minor framing repairs, no major structural or electrical work.
• Schedule: mobilize no earlier than 1 Nov 2024; finish by 31 Mar 2025.
• Procurement: single‑prime sealed proposals, 14 % MBE/DBE subcontract goal, 90‑day bid guarantee, liquidated damages $230/day.