The contract is for the replacement of HVAC equipment at the East Lake Library. The work includes the installation of two Trane 10-ton condensers and a Trane 7.5-ton split system. The contract has a budget of $107,050. The key points of the contract are:
* Installation of (2) Trane 10 ton condensers w/ (1) 20 ton Trane vertical A/H
* Installation of Trane 7.5 ton split system / A/H vertical
* Connection to existing refrigerant lines, ductwork, and controls
* 5-1-1 warranty for the equipment
* 3% charge for credit card payment upon completion.