The Coon Creek Bank Stabilization project involves stabilizing a portion of the southern bank of Coon Creek within Coon Rapids Dam Regional Park. The project requires excavation, armoring with riprap, and hauling excess material off-site. The contractor will need to coordinate with the Coon Creek Watershed District (CCWD) for technical guidance and field support. The project must be completed by March 15, 2024. Some key aspects of the project include:
• Excavation of the eroded bank to a uniform slope of 2 horizontal to 1 vertical
• Armoring with riprap
• Hauling excess material off-site
• Importing topsoil and riprap
• Removing portions of the existing trail, culverts, and trees to facilitate grading and excavation
• Completing all work in or near the water by March 15, 2024