The contract is for the design of equipment for the replacement of Well No. 2 (Well 5) in the GVID water system. The scope of work includes demolition, earthwork, pump discharge pipeline, pump-to-waste, wellhead pump and piping, site enclosure, and electrical/instrumentation design. The contract also includes construction administration and inspection services. The project is expected to take 15 months to complete, with a budget of $299,984. The contract was awarded to Consor North America, Inc.
Some key points about this contract include:
• The project involves the design of equipment for a new well in the GVID water system.
• The scope of work includes multiple components, such as demolition, earthwork, and electrical design.
• The contract includes construction administration and inspection services.
• The project is expected to take 15 months to complete.
• The budget for the project is $299,984.
• The contract was awarded to Consor North America, Inc.