The contract is for a Reverse Osmosis Membrane Study and Replacement at the RO Water Treatment Plant. The scope of work includes pilot testing, membrane selection, and installation. The contract has a total fee of $484,320.00 and is set to expire on August 5, 2024. The contract was awarded to Kimley-Horn and Associates, Inc.
• The contract includes tasks such as pilot testing protocol and membrane selection, pilot unit installation and startup, and membrane procurement documents.
• The contract has a total duration of 5 years.
• The contract was approved by the City Council on July 22, 2019.
• The contract has a change order that increases the task 2 cost by $10,000.00 to cover extra fees in renting a different pilot skid.