The contract is for the Dick Creek Diversion & Fish Barrier Improvements project, located in Wyoming. The project involves the removal of the existing diversion and fish barrier structure, the installation of a new concrete diversion and fish barrier, and general grading and ditch improvements. The contract was awarded to two vendors, LCI Trucking and Urick Precision Construction, with bid amounts of $1,079,436.14 and $749,936.17, respectively.
• The project requires a mandatory pre-bid meeting, which was held on December 5, 2024.
• The contract involves the installation of a new siphon under North Dick Creek.
• The project requires the submission of a bid bond, which must be in the form of a bid bond, cashier's check, or certified check.
• The contract has a total bid amount of $1,079,436.14 for LCI Trucking and $749,936.17 for Urick Precision Construction.