This contract awards the renovation of the Spokane Water Department’s Meter Shop and Main Office (Phase 1) to a single general‑contractor. The work includes interior demolition, structural modifications, new “gasket” construction linking the Meter Shop to the Administration Building, brick‑masonry repair, and associated MEP upgrades. The project is funded by the City of Spokane and is subject to Washington State public‑works requirements, including bid bonds (5 % of total bid), performance/payment bonds (100 % of contract price), prevailing‑wage compliance, and liquidated‑damage penalties of $1,000 per working day after the July 1 2026 substantial‑completion deadline.
• Scope: interior remodel, new addition, masonry repair (up to 500 sf), and coordination of HVAC, plumbing, electrical, fire‑protection, and site utilities.
• Schedule: bids due 10 Feb 2025, award 12 Feb 2025, work must start within 10 days of NTP, substantial completion by 1 July 2026.
• Financials: Engineer’s estimate $4.5 M; award amount $4,630,417; 5 % bid security required.