The City of Edgewater awarded a municipal‑utility construction contract for the design‑build installation of approximately 22,000 linear feet of reclaimed‑water pipelines (PVC and HDPE) across three phases, including valve installations, curb & gutter work, and associated roadway restoration. The award was made to Masci Corporation in a competitive sealed‑bid process, with a unit‑price schedule and mandatory Davis‑Bacon, Buy‑America, and SRF compliance. The project is funded through the Florida Department of Environmental Protection Clean Water State Revolving Fund, with an engineer’s budget of roughly $4 million and a total award value of $3.58 million. Key contractual requirements include performance and payment bonds (100 % of contract amount), a 300‑day substantial‑completion deadline, liquidated damages of $500 per day, and extensive environmental and safety certifications.