The City of Issaquah is soliciting qualified contractors to furnish and install four dual‑port Level 2 electric vehicle (EV) charging stations at Tibbetts Valley Park. The work includes providing the ChargePoint CT6000 equipment, site preparation, civil work, electrical interconnections, signage, lighting, ADA‑compliant parking spaces, testing, commissioning, and a one‑year warranty. The contract is for a one‑year term with an option to extend, and work must be completed no later than June 30 2026‑2027, with construction slated for November 2026 through June 2027. The bid must be submitted electronically by October 19 2026.
• Scope: supply and install four dual‑port Level 2 chargers (three standard, one with 23‑ft cord).
• Required deliverables: equipment, civil/site work, electrical installation, networking, testing, signage, lighting, ADA compliance, warranty, documentation.
• Schedule: award Nov 6 2026; construction Nov 16 2026 – June 15 2027; final completion June 30 2027.
• Mandatory requirements: prevailing‑wage compliance, UL‑certified new equipment, remote diagnostics, payment‑card capable, ADA accessibility, one‑year warranty.
• Budget: fixed‑price bid covering equipment, labor, permitting, and all related costs.