The City of Bryan is seeking qualified contractors to replace 12‑inch and 8‑inch waterlines along the north and south right‑of‑way of William J. Bryan Parkway, including installation of new fire hydrants and service transfers. The project budget is $450,000, with construction slated to begin October 26 2026 and be completed within 60 working days (targeted completion January 22 2027). The contract includes responsibilities for permits, inspections, performance and payment bonds, insurance, warranties, and delivery of operation‑and‑maintenance manuals. Proposals must be submitted electronically (or sealed hard copy) by September 2 2026, with a non‑mandatory pre‑proposal Zoom meeting on August 24 2026 and a Q&A cutoff on August 25 2026. The City will award the contract by October 13 2026, with a notice to proceed expected shortly thereafter.
• Scope: Replace 12” & 8” waterlines, install fire hydrants, service transfers.
• Budget: $450,000 (inclusive of all costs).
• Schedule: Bid opening Sep 2 2026, award Oct 13 2026, construction Oct 26 2026 – Jan 22 2027 (≈60 working days).
• Requirements: Bonds (5% bid bond, performance & payment bonds), insurance (CGL, workers’ comp, auto, pollution, etc.), contractor registration score ≥70, felony disclosure, compliance with EO 11246.
• Submission: Electronic via BrazosBid portal or sealed envelope to Purchasing Dept., 2611 N. Earl Rudder Frwy, Bryan, TX.
• Contact: Catherine Benavides, Purchasing Department, (979) 209‑5505, [email protected]