This contract is for the maintenance garage extensions at the Kennebunk and Gray maintenance facilities, as well as the installation of a new heating system at the Crosby Maintenance Facility. The work includes extending and rehabilitating two maintenance garages, replacing existing siding and roofing, installing electrical conduits, and adding unit heaters. The contract also includes the installation of new lighting fixtures and accessories. The contractor is required to obtain all necessary permits and ensure that the work conforms to the National Electrical Code and other applicable codes. The contract has a completion date of November 15, 2018, and substantial completion is expected by October 31, 2018.
• The contract includes the extension and rehabilitation of two maintenance garages in Kennebunk and one in Gray.
• The work includes replacing existing siding and roofing with metal siding and roofing.
• The contractor is required to install electrical conduits and add unit heaters.
• The contract includes the installation of new lighting fixtures and accessories.
• The contractor is required to obtain all necessary permits and ensure that the work conforms to the National Electrical Code and other applicable codes.
• The contract has a completion date of November 15, 2018, and substantial completion is expected by October 31, 2018.