This contract awards the design, fabrication, and installation of an updated way‑finding and signage system for the Terminal A/B garage at George Bush Intercontinental Airport (IAH). The scope covers the manufacturing of vehicular and pedestrian signs, graphic design adhering to specified standards, mounting hardware, and integration with existing parking guidance systems. The contract includes MWBE participation goals (16 % MBE, 7 % WBE) and requires compliance with City of Houston procurement policies, bonding, insurance, and payroll reporting. The awarded contractor, Intex United, Inc, will execute the work under a stipulated‑price agreement valued at approximately $1.8 million, with a 260‑day performance period.
• Manufacture, supply, and install signage and way‑finding graphics for the A/B garage (Levels 1‑8).
• Integrate new signs with existing Automated Parking Guidance System hardware.
• Meet City‑mandated MWBE participation goals and adhere to safety, insurance, and bonding requirements.