This public‑sector project involves extensive site work and retaining‑wall construction at the Horeb Springs location. The scope includes site access and staging, demolition and excavation, replacement of stairs and railings, sidewalk and colored‑concrete work, installation of a new Redi‑Rock (rock‑fill) retaining wall, and the removal/reinstallation of safety post‑and‑rope barriers. Two mandatory alternates are listed: repair/renovation of an existing wall (500 sf) and full replacement of that wall. The bid tabulation shows two competing firms—All‑Ways Contractors, Inc. and Lowe Underground, Inc.—with base‑bid totals of $488,906 and $676,580 respectively, plus alternate costs that could raise total values toward $750 k. No award decision, contract number, or agency contact details are included in the excerpt.
• Major work: 2,820 sf new retaining wall (Redi‑Rock) plus associated excavation and concrete work.
• Mandatory alternates require either 500 sf wall repair or full replacement, adding $28‑$60 k (All‑Ways) or $60‑$73 k (Lowe).
• Bidding opened on June 13 2025 11:00 AM CDT; no closing or award dates are provided.