The contract is for the refurbishment of the Silver Lake Plant Unit 3 cooling tower structure. The base work scope addresses the structural issue, and several alternate work scopes were included to facilitate the conduct of work that may be necessary for proper refurbishment. The contract was awarded to Cooling Tower Depot Inc. for $77,472.00, which includes a $10,000 contingency. The project duration is 60 days. Key aspects of the contract include:
• Refurbishment of the cooling tower structure
• Alternate work scopes for additional work that may be necessary
• Contingency fund of $10,000
• Project duration of 60 days
• Awarded to Cooling Tower Depot Inc. for $77,472.00