The City of Spokane awarded a contract to LEXICON, INC. DBA HERITAGE LINKS for the complete renovation of the irrigation system at Downriver Golf Course, a municipal 18‑hole facility. The scope includes design, supply, and installation of new HDPE mains and laterals, over 1,000 sprinkler heads, valve assemblies, a central computer control system, a potable‑water line, and related electrical and conduit work. The project is funded by city resources, follows Washington prevailing‑wage rules, and carries a one‑year warranty with liquidated damages for late completion. Key points:
• Awarded via public competitive bidding (PW ITB 5399‑21) with a unit‑price bid form; final award price $2.86 M.
• Construction start planned within 10 days of award; substantial completion required by 1 June 2022.
• Includes optional rock‑excavation and additional irrigation heads at a second site (Esmeralda Golf Course) as alternates.