The contract is for the replacement, upgrade, and expansion of the EKU Security Emergency Call Stations across the Richmond, Kentucky campus. The scope of work includes furnishing all labor, materials, equipment, and services necessary for the complete project. The project is expected to be completed within 210 calendar days after the start date. The contract was awarded to Delta Services, LLC, Schiller Hardware, and Art's Electric, with bid prices of $1,583,000.00, $1,718,935.00, and $2,517,300.00, respectively.
• The project includes power and network connectivity to exterior installed stations.
• The infrastructure is to be coordinated with existing head-end equipment and power distribution sources.
• The contractor is to include all labor and materials for a complete system, including programming, testing, and coordination with EKU stakeholders.
• Liquidated damages of $200 per day until substantial completion and $100 per day until final completion will be applied.
• A bid bond of 5% is required, and full payment and performance bonds will be required for the awarded contractor.