This contract awards the replacement of two 45 kW/45 kVA three‑phase UPS units in the Renne Library Data Center at Montana State University, including removal of legacy equipment, asbestos‑containing floor and wall surfacing, new conduit and wiring, and full commissioning and testing. The scope also covers the installation of static and maintenance bypass cabinets, battery cabinets, and integration with existing Emergency Power‑Off (EPO) systems. Work must be coordinated with university facilities, adhere to strict data‑center clean‑room protocols, and be performed during regular business hours with at least two‑week outage notice. The project is funded by the State of Montana, solicited through a sealed‑bid competitive process, and was awarded to The Third Element, Inc. (with Standard Electric noted as a subcontractor). Key points:
• Replacement of two UPS modules (45 kW each) with 15‑min battery runtime and integrated bypass.
• Selective demolition of asbestos‑containing floor tile and wall surfacing, requiring EPA‑compliant disposal.
• Installation of new electrical distribution (conduits, raceways, labeling) per NFPA 70 and UL 1778 standards.
• Completion required by 19 Aug 2026; base bid amount $121,461.