The Yeon Cooling Tower Replacement contract involves the replacement of a cooling tower at the Yeon Facility in Portland, Oregon. The contract was awarded through an Invitation to Bid (ITB) process, with a mandatory pre-bid conference and pre-qualification requirements. The contract terms and conditions, as well as the project manual, are available on the Buyer Attachments page of the Sourcing Event. The contract aims to reuse, salvage, or recycle as much waste material as economically feasible and to obtain maximum utilization of State of Oregon certified MWESB firms.
• The contract is for the replacement of a cooling tower at the Yeon Facility.
• The contract was awarded through an ITB process.
• The contract has pre-qualification requirements.
• The contract aims to promote sustainable business practices.
• The contract has a project manual and contract terms and conditions available on the Buyer Attachments page.
• The contract has a mandatory pre-bid conference.