The contract is for the installation of electric vehicle charging infrastructure at the Public Works Campus in Clearwater, Florida. The project involves the installation of seven duplex GFI receptacles on the east side of Building 1, which will provide electric service for simultaneous charging of seven trucks at 115VAC, 12A each. The contract was awarded to Peak Power Services, Inc. for a total amount of $26,312. The contract duration is 15 days, and the work is expected to be completed by May 31, 2024.
Key aspects of the contract include:
* Installation of electric vehicle charging infrastructure
* Seven duplex GFI receptacles to be installed on the east side of Building 1
* Electric service to support simultaneous charging of seven trucks at 115VAC, 12A each
* Contract duration: 15 days
* Contract award amount: $26,312
* Contractor: Peak Power Services, Inc.
* Project location: Public Works Campus, 22211 US Highway 19 North, Clearwater, Florida