The contract is for the Rapid Transit Addition project, which involves a twelve-bus bay addition to the bus storage facility at 760 Centre Street. The project has multiple components, including a base bid and alternative bids. The contract was awarded to multiple vendors, with the base bid prices ranging from $954,900 to $1,041,500. The project also includes the purchase of equipment, such as articulated wheel loaders and skid steer loaders.
• The project involves a twelve-bus bay addition to the bus storage facility.
• The contract has multiple components, including a base bid and alternative bids.
• The contract was awarded to multiple vendors.
• The project includes the purchase of equipment, such as articulated wheel loaders and skid steer loaders.
• The base bid prices range from $954,900 to $1,041,500.