This contract concerns the installation of two FLO CoRe+ Level‑2 electric‑vehicle charging stations in the Huntington Parking Garage owned by Cuyahoga County. The work is limited to electrical installation, conduit and wiring, fire‑stop compliance, and on‑site verification; the charging units themselves will be purchased separately. No subcontracting is permitted, and bidders must be registered in the county’s purchasing system and complete a mandatory on‑site visit prior to submitting a bid. The award amount is $9,875, and the solicitation was opened on May 8 2025 and closed on May 14 2025, with the award confirmed on May 16 2025.
• Scope: Install two FLO CoRe+ 7.2 kW EV chargers, provide conduit, wiring, grounding, and fire‑stop work per NEC‑2023 and Ohio Building Code.
• Requirements: Prime contractor only, must be registered in the county’s Infor system and with the County Inspector General, and must complete a mandatory onsite visit.
• Contacts: Adam Miller (field buyer) and email [email protected] for scheduling the onsite visit.