This contract calls for the fabrication of a single steel module for the Nelson Lagoon Power System Upgrade, including all exterior attachments such as stairs, landings, loading docks, and radiator/cooler platforms. The vendor must deliver a fully welded and painted steel structure, complete with fasteners, lifting eyes, insulation, and coating, ready for loose‑ship to the Alaska Energy Authority’s Anchorage facility. The work is strictly fabrication; site foundations, roofing, doors, windows, and power‑generation equipment are excluded. The solicitation was issued as an open competition (ITB #23096) with a firm‑fixed‑price lump‑sum award, and the contractor must meet a delivery deadline of 18 calendar weeks after award, with liquidated‑damage penalties of $250 per day (capped at $5,000). Key compliance requirements include federal assurances (Davis‑Bacon, anti‑kickback, debarment, etc.), required insurance coverages, and strict inspection and progress‑reporting protocols.